Burnet 16-Inch Northwest Water Transmission Line

Burnet 16-Inch Northwest Water Transmission Line

Burnet 16-Inch Northwest Water Transmission Line

Burnet 16-Inch Northwest Water Transmission Line



PROJECT NAME:16-Inch Northwest Water Transmission Line
LOCATION:Burnet, Texas
OWNER:City of Burnet
YEAR COMPLETED:2005
CONSTRUCTION COST:$715,000
OWNER REPRESENTATIVE:David Vaughn, Assistant City Manager
 512.756.4858

PROJECT DESCRIPTION:This project involved design of a 16-inch water transmission main through the City of Burnet. The transmission main consisted of approximately 10,000 linear feet of ductile iron pipe used to supply additional water at higher pressure (1570' MSL) to existing residential areas not meeting the Texas Commission on Environmental Quality minimum pressure requirements. In addition, this transmission main provides water to proposed developments in northern Burnet which are located in this higher pressure plane.

SERVICES PROVIDED:Project management for the entire project development including submittal to the USDA - Rural Development Services for grant assistance for the project. Services included Preliminary Engineering Report, Environmental Assessment, Final Design Phase Services, Easement Acquisition, TxDOT Permitting, Grant Application, Bid Phase Services, and Construction Phase Services including Project Inspection.
Previous Printable Version Next