PROJECT NAME:Lower Colorado River Authority Wastewater Treatment Plant
LOCATION:Austin, Texas
OWNER:LCRA
YEAR COMPLETED:2006
CONSTRUCTION COST:$640,980
OWNER REPRESENTATIVE:Brad Hill, Project Manager
 512.473.3543

PROJECT DESCRIPTION:

          Clarifier Mechanism

This project involved construction of a 50,000 gallon per day extended aeration activated sludge wastewater treatment plant, 3,250 linear feet of six-inch effluent line and 3,000 linear feet of SDR 26 pressure sewer line. A pre-cast concrete treatment unit consisting of a 44,600 gallon aeration tank, 18,500 gallon reaeration tank, 22,000 gallon clarifier, chlorine contact chamber and sludge holding tank were installed on a structural slab designed by Thonhoff Consulting Engineers. Included in the project scope were all required piping interconnections, electrical infrastructure, telemetry, and site work.

Design constraints included minimizing construction impact due to the construction of the treatment plant inside the Matagorda Bay Nature Park and the project site being located approximately seven feet below the 100-year flood elevation.

  
SERVICES PROVIDED:Environmental Permitting, Preliminary Design, Final Design, Bid Phase, Re-Bid Phase, Construction Phase for WWTP Installation and Warranty Assistance Services.